Thursday, April 28, 2011

ADOT will work on SR 188 May 2-4 - Expect delays between Punkin Center and SR 87

Lane restrictions and delays on SR 188 next week

                                                                                          
The Arizona Department of Transportation will close lanes on a 10-mile segment of State Route 188 between Punkin Center and State Route 87 from Monday, May 2 through Wednesday, May 4 as maintenance crews apply rejuvenating oil to protect and preserve the pavement.
 
Crews will work on three to four miles of the highway each day and apply the oil to both sides of the roadway.  Traffic will be restricted to one lane through the work zone.  Flaggers and a pilot car will direct traffic in alternating directions using the single lane that is open.  Drivers can expect delays of 10 to 15 minutes.
 
ADOT advises drivers to proceed through the work zone with caution, slow down, and be alert for construction equipment and personnel.
 
For more information about this project, please contact Southern Globe District Senior Community Relations Officer Teresa Guillen, at 602-828-8075 or tguillen@azdot.gov. Local media should contact the ADOT Public Information Office at news@azdot.gov or 1.800.949.8057. Visit www.facebook.com/azdot or www.azdot.gov for more information about ADOT.

Additional information about ADOT in the Rim Country: 
 
STATE ROUTE 260 DOUBTFUL CANYON

Clearing Operations Continue
Crews will continue logging operations and removal of timber to accommodate the highway improvements the week of May 2. Temporary flagging may take place periodically to assist in allowing trucks and heavy machinery access to the highway and project work zone.  Although no lane closures or restrictions are anticipated at this time, drivers are asked to use extra caution and expect brief delays through the work zone.  The speed limit will be reduced to 45 miles per hour and will be strictly enforced.

STATE ROUTE 260 LITTLE GREEN VALLEY
Hauling of Base Material
ADOT crews will begin hauling base material the week of May 2 between milepost 262 and milepost 267 in preparation for paving the new eastbound lanes of the Little Green Valley widening project.  Hauling of base material is scheduled between 4 p.m. and 9 p.m. Monday through Thursday. Motorists can anticipate brief delays to allow trucks and machinery to enter and exit the highway during extended work hours. Hauling of base material is scheduled to continue through May 20.  The speed limit is reduced to 45 miles per hour and there is no passing in the construction zone.

 Lane closures scheduled for State Route 70 near Globe beginning Monday
The Arizona Department of Transportation is scheduled to apply a coat of rejuvenating oil to the roadway surfaces on State Route 70 from Globe to San Carlos Indian Reservation beginning Monday (May 2) through Thursday (May 5). Work crews will direct motorists through the lane closures in the work zone. Drivers can expect delays of up to 30 minutes.
 
ADOT will be working on northbound and southbound SR 70 from mileposts 251 to 271 southeast of Globe. Lane closures will be in effect from 7 a .m. to 5 p.m.
 
The construction schedule is subject to change due to a variety of reasons, including weather, material availability and mechanical difficulties. As always, drivers are reminded to proceed through the work zone with caution, slow down, and be alert for construction equipment and personnel.